The restoration of roads in the villages (of the 110 villages) in Yelahanka constituency limits is going on in a speedy manner and today,the BBMP Chief Commissioner Gaurav Gupta instructed the officials to accelerate the work speed further.
Speaking after inspecting the road restoration works at Ananthapura,AMS layout limits in Yelahanka constituency,he said that, the roads in the city should be motorable well enough.
He also instructed the officials to finish the asphalt works in major roads and also the restoration work of village roads within the scheduled period of time.
Roads,footpaths should be restored ensuring the quality work where the BWSSB’s works related to the drinking water and the drainage have been finished.
No residents should face problem at any cost, the Gaurav Gupta instructed the officials.
Executive Engineer,Sudhakar Reddy,explaining about the works to the Chief Commissioner,said that,among the 110 villages,8 villages (Ananthapura,Chikkabettahalli, Doddabettahalli, Kenchenahalli, Harohalli,Nagenahalli,Vaderapura, Govindapura),are coming under the Yelahanka constituency.
The road restoration is being held in all those villages except Vaderapura and Govindapura.
“The BWSSB has dug up 151 km of road to take up the works related to drinking water and drainage.Of that 151 km, the BBMP, has restored 60 km of road.
The pending 91 km of road will be restored within the prescribed time duration”the Executive Engineer explained to the Chief Commissioner.
Appreciations to BBMP’s work
All the crossroads,including footpaths at the AMS Layout in Attur ward limits have been asphalted.
On this,local resident Mr.Bellave appreciated the BBMP’s work.BBMP is doing excellent work he said.
Zonal Joint Commissioner,Poornima, Zonal Chief Engineer,Ranganath and other concerned officials were present on the occasion.